Over the last two decades, Champaign Unit 4 has issued hundreds of millions of dollars in bonds and other financing obligations to rebuild schools, construct new facilities, renovate aging buildings and expand campuses across the district.
Indeed, a new bond referendum is on the November 2026 ballot, asking voters to approve $192 million for new school construction projects and renovations.
But a CU-CitizenAccess.org review of official bond filings, district oversight committee records, board minutes and multi-year project cost updates revealed that several construction projects exceeded their preliminary cost estimates presented to voters and tax payers, while changes to the scope of other projects contributed to increases in overall construction budgets.
Bonds are long-term loans issued by school districts to pay for large construction projects. The debt is repaid over time, usually through property taxes or other pledged revenues.
Those borrowing decisions did not occur all at once. Instead, financing for construction, as well as other purposes, was spread across multiple bond issuances over more than a decade.
Since 2010, Champaign Unit 4 has issued several major bond and other financing series to support school construction and renovations, alongside additional transactions to refinance or restructure existing debt, according to district audits and official bond filings.
Two major periods of construction financing followed voter-approved referendums:
2010 financing — $86.8 million
Following Champaign County voters’ approval of the 1% school facilities sales tax in 2009, Unit 4 issued two bond series and two lease-obligation series totaling approximately $86.8 million in original principal. The obligations were supported by anticipated sales tax revenue and property tax security, according to the district’s 2010 EMMA Official Statement.
Operated by the federal Municipal Securities Rulemaking Board, EMMA, which stands for Electronic Municipal Market Access, is a public database that provides access to municipal bond filings, including details on borrowing amounts, interest rates and the purposes of bond issuances.
Separately, records presented to the Promises Made, Promises Kept committee in January 2015 reported approximately $87.49 million in unaudited expenditures across capital funds 60 and 61 through fiscal year 2014. These expenditures included multiple funding sources and cannot be treated as the final cost of projects financed solely by the sales tax.
2016 construction referendum — $183.4 million authorized
Voters approved $183.4 million in school construction bonds, of which approximately $110 million was issued in 2017 and another $73.4 million in 2020. Including $25 million in existing district funds, the original construction program had a budget of $208.4 million.
By March 2022, the district’s updated program budget had reached approximately $273.4 million, an increase of $90 million of what voters saw on the ball but an increase of $65 million, or 31.2%, over the original overall budget, including reserves.
In addition to these construction-related bond issues, Unit 4 undertook several other financing transactions:
- Series 2019 General Obligation Refunding School Bonds — $67.72 million:
- Issued to refinance outstanding debt from the 2010B and 2010D financing series, including Build America Bonds. According to the district’s FY2020 audit, the refinancing was projected to reduce total debt-service payments by approximately $22.1 million over 17 years.
- Series 2020B General Obligation Limited Tax Refunding School Bonds — $6.98 million:
- Issued to refinance approximately $7.54 million in outstanding bonds from 2012 and 2013. The district reported projected debt-service savings of approximately $946,603 over 10 years.
- Series 2021 General Obligation Debt Certificates — $20 million:
- Issued in July 2021 as a separate borrowing transaction, with a stated interest rate of 1.45% and scheduled repayments through June 2031.
These transactions served different purposes. While the 2019 and 2020B refunding bonds replaced existing obligations rather than financing additional construction, the 2021 debt certificates represented a separate issuance of debt. Together, the transactions illustrate how Unit 4 has financed school improvements and managed repayment obligations over multiple years.
According to Unit 4’s fiscal year 2025 audited financial statements, the district carried approximately $258.5 million in outstanding long-term liabilities as of June 30, 2025, down from $276.4 million the previous year. Of that total, approximately $219 million was recorded as bonds payable.
Despite the decline in long-term liabilities, the district’s annual debt-service payments changed little. Principal and interest payments from its Debt Service Fund totaled approximately $27 million in fiscal year 2025, compared with $27.2 million in 2024. The fund recorded approximately $17.3 million in property tax revenue in 2025, alongside $8.4 million from the countywide school facilities sales tax and additional investment income.
2009: Referendum
Unit 4 financial management has been under intense scrutiny since 2009, when Champaign County voters approved a 1% School Facilities Sales Tax, a countywide measure promoted as a way to fund school construction without raising property taxes.
According to the referendum fact sheet, Unit 4 would receive about $7 million per year. This revenue would support expanding Garden Hills, rebuilding Booker T. Washington, constructing a new school in Savoy and making improvements at other elementary schools.
Once approved, this referendum said the first $14.5 million would be used to reduce property taxes within the district. This was said to save the taxpayer with a home valued at $150,000, about $32 in property taxes. At the time, the district emphasized that property taxes already made up 66% of its entire budget and that years of overspending had recently been reversed.
After a 10-year trend of overspending the approved budget, Unit 4 had just regained back a “Recognized” financial rating, which is the highest category assigned by the Illinois State Board of Education, serving as evidence the district could responsibly manage new construction funding in order for voters to pass this referendum.
To reinforce public trust, Unit 4 committed to creating an oversight group called the Promises Made, Promises Kept Committee for the tracking of every expenditure tied to the sales tax revenue. The district said funds would be kept in a separate account and used exclusively for land acquisition, renovations and new school construction.
“The Promises Made, Promises Kept Committee is run by former board member Arlene Blank, and it was put in place with several different members throughout the community to make sure the district carried out what we were originally intending to do with the 1% sales tax,” Matthew Foster, former Unit 4 executive director of business services and committee member, said in a 2013 video by the district highlighting its, at the time, new and renovated facilities.
The 2010 Bond Series
While the district portrayed the sales tax referendum as a sign of strict fiscal discipline, in the years that followed, oversight records documented expenditures that differed from some of the preliminary estimates presented to voters.
Months after Champaign County voters approved the 1% sales tax in 2009, Unit 4 formally issued four bond and lease certificate series in 2010. The board used some of the projected sales tax revenue to back it the bonds.
Altogether, the borrowing totaled $86.8 million across four bond and lease obligation series in 2010, according to the district’s 2010 EMMA Official Statement.
2010 Bond Series
Issuance Breakdown
| Year Issued | Bond Series | Initial Amount | Interest Rate | Status / Notes |
|---|---|---|---|---|
| 2010 | Series 2010A: General Obligation Capital Appreciation Bonds (Alternate Revenue Source) | $2,862,815 | 4.61% | Capital Appreciation Bonds; listed in Note 7 (FY2020) as part of the alternate revenue structure; matured 2024. |
| 2010 | Series 2010B: Taxable General Obligation Build America Bonds (Alternate Revenue Source) | $49,790,000 | 6.30% | Build America Bonds Refunded in 2020 by Series 2019 Alt. Revenue Bonds; refunding reduced debt service by $22 M and produced $10.3 M gain (FY2020 Audit, Note 7). |
| 2010 | Series 2010C: Capital Appreciation Lease Obligations (Alternate Revenue Source) | $ 11,380,280 | 4.03-4.50% | Paid off in 2022 (FY2022 Audit). |
| 2010 | Series 2010D: Taxable General Obligation Lease Obligations (Alternate Revenue Source) | $ 22,725,000 | 1.10-4.00% | Refunded in 2020 as part of Series 2019 Alt. Revenue Bonds (FY2020 Audit). |
Through the years, the Promises Made, Promises Kept oversight committee tracked all construction expenses for the projects identified during the sales tax campaign through funds 60 and 61. In a 2015 report, the committee found expenditures totaled $87.49 million.
Under federal and state accounting rules, school districts can only spend building-related dollars out of these capital funds, which means the totals in funds 60 and 61 reflect a mix of sources that supported the work: local property taxes, state or federal dollars and any grants tied to capital improvement — not only the district’s share of the 1% countywide sales tax.
The district began using sales tax dollars to abate property taxes during the 2009-10 school year, reducing taxes. Sales tax revenue was also used for smaller deferred-maintenance items, such as roof replacements and tuckpointing, while interest earned on the funds was applied to furnishings for refurbished and newly built schools, according to the oversight committee’s website.
Because the committee’s information is no longer on the Unit 4’s official website, those meeting records had to be obtained through the Wayback Machine, a nonprofit project that archives web pages from millions of websites.
2010 Breakdown & Updates
Final Update (as of 2015): $87.49M
| School / Project | Original Estimate (2009 Referendum) | Reported Project Expenditures (PMPK 2015) | Change | Notes |
|---|---|---|---|---|
| Garden Hills Elementary | $12.0M | $13.89M | +$1.89M | (Completed August of 2012) |
| Booker T. Washington STEM | $18.0M | $16.34M | –$1.66M | Stayed near target; small credits/adjustments.(Completed August of 2011) |
| Carrie Busey (Savoy) | $18.0M | $18.32M | +$0.32M | (Completed August of 2012) |
| Westview Elementary | $4.5M | $9.71M | +$5.21M | |
| Bottenfield Elementary | $4.5M | $9.63M | +$5.13M | |
| Kenwood Elementary | $4.5M | $1.86M | −$2.64M | (Completed 2015) |
| Robeson Elementary | $4.5M | $5.58M | +$1.08M | |
| Franklin Middle School | Not Listed | $6.26M (FY13) | Added later on, as they do not appear in the referendum. | |
| Edison Middle School | Not Listed | $1.043M (FY13) | Added later on, as they do not appear in the referendum. | |
| Central High School | Not Listed | $1.70M | ||
| Total (funds 60 + 61) | $68.9M | $87.49M | + $18M (25%) | The $87.49 million represents cumulative expenditures across funds 60 and 61 through FY2014. These totals are not directly comparable and do not establish an overall construction cost overrun. |
Source: Promises Made, Promises Kept Jan. 8, 2015 report
Unit 4’s 2009 referendum materials projected approximately $4.5 million in improvements for each of the remaining elementary schools. However, financial records presented to the oversight committee in January 2015 showed that Westview and Bottenfield elementary schools had accumulated $9.71 million and $9.63 million in expenditures, respectively, through fiscal year 2014, more than double the preliminary estimates.
Despite some overruns, the district emphasized the positive outcomes of these projects. In a district-produced video released in 2013 highlighting new and renovated facilities, then-Superintendent and oversight committee member Judy Wiegand pointed to a series of elementary school projects completed or underway using the 1% sales tax.
She said the district’s broader objective was student-focused, adding that “the goals of this district are to ensure that all of our students are prepared to be successful in post-secondary endeavors.”
Additional borrowing in 2012 and 2013
The district issued two follow-up bonds during this period, both classified as General Obligation Limited Tax School Bonds. Unlike refinancing bonds, these issues raised new money for the district’s working cash fund to finance capital improvements.
In 2012, Unit 4 issued approximately $9.58 million in bonds. According to the district’s official statement, the proceeds were deposited into the working cash fund to finance capital projects, including the installation of geothermal systems, windows and lighting at Jefferson and Franklin middle schools.
A year later, in 2013, the district borrowed another $2.99 million through a similar bond issue. Those funds supported district-wide wireless infrastructure improvements and renovations to the district’s transportation facility.
2012 & 2013 Bonds
Issuance Breakdown
| Year Issued | Bond Series | Amount | Interest rates |
|---|---|---|---|
| 2012 | Series 2012 | $9,575,000 | 2.00-3.00% |
| 2013 | Series 2013 | $2,990,000 | 2.00-2.50% |
Neither issue refinanced existing debt. Instead, the bonds represented approximately $12.5 million combined in additional borrowing, adding new obligations to the district’s repayment schedule.
In 2020, the district refinanced the remaining debt from both issues by issuing approximately $6.98 million in Series 2020B General Obligation Limited Tax Refunding Bonds. The proceeds were used to retire approximately $7.54 million in outstanding debt from the 2012 and 2013 bonds, with the goal of reducing future debt-service costs.
The 2016 Referendum
After “reversing a 10-year trend of overspending the approved budget,” the district said it could responsibly manage new construction funding in order for voters to pass the 2009 sales tax referendum, as per the 2009 referendum fact sheet.
Yet, this trend emerged again with a new referendum voters approved on the ballot in 2016.
While Unit 4 had previous referendums, the most publicized was the 2016 referendum, which authorized up to $183.4 million in new bonds, the amount described by the News-Gazette as the “most expensive referendum in Champaign County history.”
Although the $183.4 million referendum was passed in 2016, it took three efforts to pass the $183.4 million property tax proposal that is paying for these construction projects.
Indeed, voters had already rejected two previous bond proposals: one in November 2014 for $149 million, and another in April 2015 for $144 million. A third, revised version went to the ballot in November 2016 with an increased price tag of $183.4 million and new configurations, which refers to the 2017 bond series tax payers will continue to pay off years later.
Public meetings leading up to the vote reflected community skepticism. In fact, Board
Member Lynn Stuckey, who had served during the two failed referendums, voted against it. As noted by the News-Gazette, Stuckey expressed concerns about the process and the regrets for not surveying the community to find out why people voted against the previous proposals.
She also expressed concerns using funding from the district’s reserves worth $25 million.
Hoping to finance the rebuilding of Central and Centennial High Schools, Dr. Howard Elementary School and other facilities, voters approved the referendum after being told it would cost the average homeowner about $23 per month, or roughly $280 annually, for twenty years, as per the School Facilities Referendum Fact Sheet. That meant the average homeowner would eventually pay a total of $5,600.
The 2016 referendum paved the way for the bond Series 2017. The fiscal year 2024 audit shows $59.4 million in principal and $12.5 million in interest remaining on the 2017 bond series, which will not be fully paid off until 2031.
Altogether, taxpayers still owed about $71.8 million in 2024 regarding that referendum alone, even as newer bonds have been issued on top of it.
According to Unit 4’s fiscal year 2025 audited financial statements, approximately $52.12 million in principal remained outstanding on those bonds as of June 30, 2025.
The district subsequently refinanced a portion of that debt through its Series 2026 refunding bonds. Sold in December 2025, the refinancing was expected to save approximately $3 million in future debt-service payments, according to the district.
2017 Bond
Issuance Breakdown
| Year Issued | Bond Series | Initial Amount | Interest Rate | Purpose (as stated in official filling) | Status / Notes |
|---|---|---|---|---|---|
| 2017 | Series 2017 | $110M | 4.00–5.00% | Issued to modernize/renovate and expand Central and Centennial High Schools, rebuild Dr. Howard Elementary, and renovate South Side, Edison, and International Prep Academy facilities. | Active (through 2031) FY2024 audit shows $59.4M principal and $12.5M interest remaining as of 2024. |
To make sure accountability was taken, the Board of Education created the Referendum Oversight Committee, which consists of a group of community members, educators and board representatives who monitor how the funds were spent for that 2016 referendum.
According to the district, the committee’s purpose was to “oversee the work of the project team at a high level and ensure community stakeholders have a voice in the decisions being made.”
Although voters authorized $183.4 million in bonds for Unit 4’s construction referendum in 2016, the district’s original budget for the projects was actually $208.4 million, including an additional $25 million from district reserves.
As construction progressed, costs continued to rise. By March 2022, the district’s updated construction budget had reached $273.4 million, which is approximately $90 million more than the amount voters had authorized in bonds.
However, because the original construction budget also included $25 million from district reserves, the actual increase was $65 million, or 31.2%, over the initial $208.4 million budget.
The following table shows how those estimates changed over time and which projects accounted for the increases:
2016 Referendum Breakdown & Updates
Referendum Approved: $183.4 million
Programmed Budget: 208.4M (Includes $25M from District Reserves)
| Year | Central HS | Centennial HS | Edison MS | Dr. Howard Elem. | South Side Elem. | IPA | Spalding Fields | McKinley Fields | Total | Change vs 2016 |
|---|---|---|---|---|---|---|---|---|---|---|
| 2017 (Original Referendum) | $87.1M | $63.3M | $15.0M | $16.1M | $11.1M | $6.0M | $3.6M | $6.2M | $208.4M | |
| 2018 Update (Dec 3) | $87.1M | $63.3M | $15.0M | $18.1M | $11.1M | $6.0M | $3.9M | $6.6M | $211.1M | +$2.7M |
| 2019 Update (December 2) | $99.4M | $74.2M | $25.1M | $17.8M | $12.4M | $6.0M | $3.9M | $6.2M | $245M | +$37.2M |
| 2020 Update (December 7) | $99.4M | $74.2M | $25.8M | $17.6M | $12.4M | $24.3M | $3.9M | $7.2M | $264.8M | +$56.4M |
| 2021 Update (December 9) | $104.6M | $75.4M | $27.2M | $17M | $12M | $25.2M | $4.4M | $7.2M | $273.5M | +$65.1M |
| 2022 Final Update (Mar 2022) | $104.5M | $75.4M | $27.2M | $17.3M | $12.2M | $25.2 M | $4.4 M | $7.2M | $273.4M | +$65M |
Among the most notable cost increases across referendum projects was International Prep Academy. Originally budgeted at $6 million until 2019, its price quadrupled to $24.3 million by 2020.

Other school projects also saw increases. Edison Middle School increased from $15 million to about $27.2 million by 2022, an increase of roughly $12.2 million, about 81%. Central High School rose from $87.1 million to about $104.5 million, an increase of roughly $17 million, or about 20%.
While some adjustments reflected expansions in scope, the scale of the increases raised questions about early cost projections, communication with taxpayers and how the district navigated inflation and contractor estimates.
In March 2019, News-Gazette editorial board criticized the school board’s decision to add $10 million in work on Edison Middle School, calling it a “distasteful bait‑and‑switch” and warning that such moves do little to inspire public confidence as it “shows a real lack of respect for voters as well as a failure to understand that many people feel overwhelmed by the cost of supporting the public schools.”
The total cost of the referendum projects would grow substantially. By March 2022, the district’s updated construction budget had reached $273.4 million, an increase of $65 million, or approximately 31%, over the original $208.4 million program budget, which included $183.4 million in voter-authorized borrowing and $25 million from district reserves, according to district project updates.
Former board member reacts

Former Board Member Gianina Baker, who was elected as president of the board in 2023, acknowledged in a 2025 interview with CU-CitizenAccess.org that rising expenditures were real.
Baker said that as the district transitioned into a technology environment, budgeting required device replacements, maintenance and repairs for unexpected damage.
“Unfortunately, the prices aren’t the same as they were in, you know, 1920,” she said.
Baker said that for major buildings like Central and Centennial, taxpayers did “absolutely” get what they were promised. Alumni who visit often “wish it had existed when they were students,” she said.
However, Baker said that while the board made significant efforts to inform residents by offering oversight meetings, some residents believed the district had overspent. She said not all residents attended those meetings or followed the information, and the district may have “missed the mark potentially sometimes” in reaching the broader public.
New bonds issued in 2019, 2020 and 2021
Unit 4 continued borrowing while the 2016 projects were still under construction. In 2019, the district issued $67.7 million in General Obligation Refunding School Bonds (Alternate Revenue Source) to refinance portions of its earlier Series 2010B and 2010D obligations.
| Year Issued | Bond Series | Initial Amount | Interest Rate | Purpose (as stated in official filling) | Status / Notes |
|---|---|---|---|---|---|
| 2019 | Series 2019 (Alternate Revenue Refunding Bonds) | $67,720,000 | 4.00% | Issued to refund earlier 2010B and 2010D Alternate Revenue Bonds, pay capitalized interest, and cover issuance costs. The goal was to lower overall debt service and interest obligations through 2036. | Active (through 2036); total debt service $108.7M (FY2020 Audit, Note 7). |
In 2020, Unit 4 issued two additional bond series totaling approximately $80.4 million. Unlike the 2019 refinancing, these issuances served different purposes: one financed construction projects approved in the 2016 referendum, while the other refinanced existing debt from the district’s 2012 and 2013 bond issuances.
The Series 2020A General Obligation School Building Bonds, totaling $73.4 million, were used to “pay a portion of the costs of the Referendum Approved Projects,” including altering, repairing, expanding, and equipping the following: Central and Centennial High Schools, Dr. Howard Elementary, South Side Elementary, the International Prep Academy and Edison Middle School.
It included the improvement of the athletic facilities at Spalding Park and McKinley Field. The district expected to complete the portion of referendum projects financed with the 2020A proceeds within three years.
Meanwhile, the Series 2020B General Obligation Limited Tax Refunding Bonds, totaling $6.98 million, were issued specifically to refund $7.54 million of outstanding 2012 and 2013 bonds.
According to the FY2020 Audit (Note 7), the refunding reduced total debt service payments by $946,603 over ten years and resulted in an economic gain of $639,193, effectively lowering interest costs while restructuring repayment under new terms.
2020 Series Bond
Issuance Breakdown
| Year Issued | Bond Series | Initial Amount | Interest Rate | Purpose (as stated in official filling) | Status / Notes |
|---|---|---|---|---|---|
| 2020 | Series 2020A:General Obligation School Building Bonds (Current Interest & Capital Appreciation Bonds) | $73,397,604 (includes $58.88M in Current Interest Bonds and $14.52M in Capital Appreciation Bonds) | 5.00% 9.00% | “Proceeds of the 2020A Bonds will be used to (a) pay certain costs of the herein defined Referendum Approved Projects, and (b) pay costs associated with the issuance of the 2020A Bonds. | Active (through 2034). |
| 2020 | Series 2020B:General Obligation Limited Tax Refunding Bonds | $6,980,000 | 5.00% | Proceeds of the 2020B Bonds will be used to (a) refund certain of the District’s outstanding bonds and (b) pay costs associated with the issuance of the 2020B Bonds.” | Paid off in 2024. |
Together, the 2020 bond issues show how Unit 4 managed overlapping obligations by using new borrowing, not only to finish construction, but also to restructure older debt that remained.
In July 2021, the district issued another $20 million in General Obligation Debt Certificates (Limited Tax). Unlike the bonds issued under the voter-approved 2016 referendum, these debt certificates were privately placed, meaning they were sold directly to institutional investors rather than on the open market.
2021 Series Bond
Issuance Breakdown
| Year Issued | Bond Series | Initial Amount | Interest Rate | Purpose | Status / Notes |
|---|---|---|---|---|---|
| 2021 | Series 2021 General Obligation Debt Certificates(Limited Tax) | $20,000,000 | 1.45% | Issued as limited-tax GO debt certificates to provide additional capital funding and restructure ongoing obligations as projects continued. | Active through 2031. Privately placed (sold directly to institutional investors). FY22 Audit |
This method allowed Unit 4 to secure immediate capital without seeking voter approval, but it also meant the district “pledged full faith and credit” to repay the debt through its annual tax levy, as per the fiscal year 2022 Audit.
The issuance carried an interest rate of 1.45%, with annual principal and interest payments scheduled through June 2031, adding another long-term obligation alongside the district’s outstanding bonds.
How Property Taxes Fit: Overview
Even after the 2009 countywide school facilities sales tax referendum, which promised voters the 1% sales tax would save the taxpayer with a home valued at $150,000, about $32 in property taxes, levies did not go down, which back then amounted for 66% of the tax.
Records from the Illinois Policy Institute show Unit 4’s levy increased from $69.8 million in 2008 to $97.7 million in 2013. That is about a 40% increase in five years.
Not much has changed, as property taxes still make up the majority of Unit 4’s funding: ranging between 55% and 64% of all district revenue over the last five years, according to the district’s audited financial statements.
In 2024, Unit 4 proposed a property-tax levy of approximately $158 million, including $17.6 million designated for debt-service payments, according to the district’s November 2024 tax notice. While the proposed overall levy represented a 7.93% increase from the previous year, the amount allocated to debt service remained virtually unchanged from 2023, when approximately $17.59 million was extended for that purpose.
Although the district’s reported long-term liabilities decreased from approximately $380 million in 2020 to $276 million in 2024, the amount of property taxes allocated to debt service remained relatively stable in recent years, at approximately $17.6 million annually between 2022 and 2024.
As of 2025, the district’s more recent figures, Unit 4’s fiscal year 2025 audited financial statements show that tax revenues increased from approximately $159 million in fiscal year 2024 to $163.6 million in 2025, accounting for 64.2% of the district’s total revenue.
Meanwhile, the reported long-term liabilities declined from $276.4 million to $258.5 million, while interest and fees decreased from approximately $7.5 million to $6.6 million.
Despite the decline in long-term liabilities, Unit 4 proposed increasing its property tax levy for debt service in 2025. According to the district’s November 2025 tax notice, the proposed total levy reached approximately $173.15 million, including $20 million designated for debt-service payments.
The proposed debt-service amount represented a 13.71% increase over the $17.59 million extended for that purpose in 2024, while the proposed overall levy represented a 13.09% increase over the previous year’s actual extension.
| Fiscal Year | Tax Revenue (Audit) | % of Revenue from Taxes (Audit) | Long Term Debt Outstanding (Audit) | Interest & Fees (Audit) | Property Tax for Debt Service Levy / Newspaper Tax Levy Proposal Notice | % of Tax Levy for Debt Service | Sources |
|---|---|---|---|---|---|---|---|
| 2020 | $121.6M | 55% | $380.2M | $7.1M | FY2020 Audit | ||
| 2021 | $137.0M | 57% | $355.8M | $8.8M | FY2021 Audit | ||
| 2022 | $142.1M | 63% | $346.2M | $8.7M | Final: $17,585,150.37 (2023 levy notice) | 12.7% | FY2022 AuditTax Levy Notice (Nov 13 2023) |
| 2023 | $154.1M | 64% | $298.6M | $8.0M | Proposed: $17,600,000.00(increase of .0844%)Final: $17,587,144.09 | 12% | FY2023 AuditTax Levy Notice (Nov 13 2023)FY2024 AuditTax Levy Notice (Nov 11 2024) |
| 2024 | $159.0M | 61% | $276.4M | $7.5M | Proposed: $17,600,000.00 (increase of .073%)Final: $17,588,601.05 | 11.5% | FY2024 AuditTax Levy Notice (Nov 11 2024) Tax Levy Notice (2025) |
| 2025 | $163.6M | 64% | $258.5M | $6.6M | Proposed:$20,000,000(increase of 13.71%) | 11.6% | Tax Levy Notice (2025) |
Outstanding long-term debt, as reported in Unit 4’s audited financial statements, includes general obligation and alternate revenue bonds, capital leases, pension liabilities, retiree healthcare obligations and other long-term commitments. The figures do not represent outstanding bond principal alone.
Property tax increase: What changed in 2025

At the Unit 4’s Board of Education meeting held on December 8, CFO Linda Matkowski told the board that Unit 4 was using a “balloon levy” for 2025 because the district still lacked final assessment data from the county.
A balloon levy is when a district requests a levy rate higher than its current projections to account for uncertainty in property values and new growth. The levy is based on equalized assessed value, or EAV, which represents the total taxable value of property in a district after adjustments and is often not finalized until months after levy requests are submitted.
Matkowski explained that the district was still waiting on confirmed figures, noting that they still “don’t have good data from the assessor’s office.”
With early assessment projections showing “almost a 13% increase across the county,” the district published a levy reflecting a 12.27% increase.
Despite this, Matkowski said she expected the final extension to land “closer to that 8%.”
She also warned that even if the tax rates drop, many homeowners may still see higher bills because reassessments are driving property values up.
As Matkowski explained, falling tax rates don’t necessarily “mean your tax bills are gonna go down, when in fact their assessment has gone up.” She emphasized that this reflects how the property tax system works, not a change in the district’s taxing authority.
That same evening, the board also approved a tax abatement for the Series 2019 bonds, meaning part of that bond payment will not rely on property tax collections. Instead, the payment will be made using other available district revenues, such as fund balances or alternate revenue sources, as permitted under the Series 2019 bond structure.
Both the 2025 levy and the 2019 bond abatement passed unanimously.
General Obligation Refunding School Bonds, Series 2026
During the December 2025 meeting, Matkowski further noted a “small” increase in the bond-and-interest rate tied to the “restructure of the bonds that just sold a couple of weeks ago,” At the same time, she added that the refinancing saved the district “almost $3 million” in long-term debt service.
This refinancing refers to the district’s issuance of $42.21 million in General Obligation Refunding School Bonds, Series 2026, using the proceeds to retire the remaining maturities of the Series 2017 School Building Bonds.
2026 Bond Series
Issuance Breakdown
| Year Issued | Bond Series | Initial Amount | Interest Rate | Status / Notes |
|---|---|---|---|---|
| 2026 | General Obligation Refunding School Bonds, Series 2026 | $42,210,000 | 5% | Active (maturities 2027–2031); replaces approx. $44.46M in remaining 2017 bond debt |
According to the official statement filed by the district and Matkowski, its purpose was to realize debt-service savings while adjusting the district’s bond-and-interest tax rate.
The Series 2026 refunding bonds restructured the repayment schedule for a portion of the district’s outstanding Series 2017 school-building debt. According to a Dec. 16, 2025 district announcement, the refinancing was expected to save taxpayers approximately $3 million in debt-service payments while retaining a final maturity in 2031.
The district reported that approximately $44.46 million in remaining 2017 debt was replaced with $42.21 million in new borrowing, reflecting interest-rate savings achieved through it.
While the 2026 bonds did not increase the district’s total construction footprint, they changed the timing of debt repayments, with the new bonds scheduled to mature between 2027 and 2031.
CU-CitizenAccess.org reviewed public filings and documents for this review throughout 2025.